The new playgrounds are done and it's been a hot and dry summer. The grass seed that was placed around the playgrounds has suffered badly. The contractors will be back to the playgrounds this fall to re-seed. If all goes well with weather we will see nice new grass next spring.
Share on Facebook
Share on Linkedin
Email this link
25 Jun 2020
We have started taking away fencing at the newly improved parks as work is completed. Please note that playgrounds are still closed for COVID-19.
Share on Facebook
Share on Linkedin
Email this link
08 May 2020
Our playground projects have been given authorization to restart construction. You will see contractors returning back to the parks to complete the new playgrounds!
Share on Facebook
Share on Linkedin
Email this link
22 Apr 2020
Due to COVID-19 restrictions, Operation Awesome Playground works have stopped. Prior to the shutdown, sites were being prepared for artificial turf safety surfacing and asphalt paving.
When COVID-19 restrictions are lifted, construction will commence again.
Thank you for your patience in this challenging time.
Share on Facebook
Share on Linkedin
Email this link
08 Nov 2019
The last two parks in our 2019 playground projects have been started by the contractors. The old playground equipment has been removed and the foundation for the new playgrounds have been constructed.
Share on Facebook
Share on Linkedin
Email this link
29 Oct 2019
The work at Fern Park is going full speed ahead! The old playground has been removed and the base for the new playground going forward. We'll be putting needed drainage pipes along with the concrete curbs soon.
Share on Facebook
Share on Linkedin
Email this link
24 Oct 2019
The playground replacement work has started at Althea Park. The contractor has removed the old playground and is starting work on the drainage pipes. The next step will be to install of the gravel for the pathways and playground area.
Share on Facebook
Share on Linkedin
Email this link
21 Oct 2019
The contractor has started work at Brookfield Park!
Share on Facebook
Share on Linkedin
Email this link
09 Oct 2019
Please stay off new playgrounds until the contractor has removed all construction fencing. Any playground that is fenced isn't ready for use yet. We want everyone to be safe!
Share on Facebook
Share on Linkedin
Email this link
09 Oct 2019
Protective construction fencing is being installed today at Meadowvale Park. Removal of the old playground will start soon.