John N. Allan Park Tennis and Basketball Improvements Project

Share on Facebook Share on Twitter Share on Linkedin Email this link

In the 2019 Capital Budget Niagara Falls City Council approved funding to advance the implementation of the recommendations of the City of Niagara Falls Tennis and Basketball Service Delivery Review.

As part of this plan, four (4) new premium tennis courts (with pickleball lines) will be constructed at John N. Allan Park. The existing basketball court at the park will also receive an upgrade and be converted to a full multi-purpose basketball /street hockey court.

  • Other works are planned within the park to support the tennis and basketball improvements, including:
  • Parking lot upgrades
  • New drainage catch basins
  • Accessible walkways
  • Seating improvements
  • Relocation of the existing natural ice skating area
  • Landscaping

In the 2019 Capital Budget Niagara Falls City Council approved funding to advance the implementation of the recommendations of the City of Niagara Falls Tennis and Basketball Service Delivery Review.

As part of this plan, four (4) new premium tennis courts (with pickleball lines) will be constructed at John N. Allan Park. The existing basketball court at the park will also receive an upgrade and be converted to a full multi-purpose basketball /street hockey court.

  • Other works are planned within the park to support the tennis and basketball improvements, including:
  • Parking lot upgrades
  • New drainage catch basins
  • Accessible walkways
  • Seating improvements
  • Relocation of the existing natural ice skating area
  • Landscaping
  • Construction Restart!

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    3 months ago

    We have recently received authorization to restart construction! You will see our contractors back to work in the coming days.

    You need to be signed in to add your comment.

    comment
    Submitting your comment
    Cancel
  • Spring 2020 Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    4 months ago

    Construction has been stopped due to COVID-19 restrictions. Prior to the shutdown, progress was being made on site drainage and parking lot works.

    Construction will resume when COVID-19 restrictions are lifted.

    Thank you for your patience in this challenging time.

    You need to be signed in to add your comment.

    comment
    Submitting your comment
    Cancel
  • Fall 2019/ Spring 2020

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    12 months ago

    Work is anticipated to commence October 2019 with completion Spring 2020. During this period of time effected areas of the park will be closed to the public.

    An artistic concept sketch has been provided for information purposes. Some further refinements to the plan are currently in progress.