24 February 2021

It is really exciting to see this project really shape up. The series of photos provided today are courtesy of Garritano Bros. LTD who is the General Contractor on the site. From the images, you can see how much work has progressed on the property. Foundations for both buildings have been set. The walls of the Market Hall have started and in the next two weeks, they will be starting on the Studio section.

Image Courtesy of Garritano Bros. Ltd.

Archaeologist have found more materials, but nothing major. Looks like some waste pits and maybe some burn pits in various areas, but work has continued on the property.

Once the walls start, the contractors will start working on weeping tile around the building and doing water proofing below grade. The team is also starting to work on some of the underground duct work.